The Armed Services Board of Contract Appeals (the “ASBCA” or “Board”) recently rejected an unprecedented request from the U.S. Army Corps of Engineers (the “Corps”) to withhold publication of a Board decision on the merits in a construction delay appeal brought by KiewitPhelps.  In a decision issued on June 25, 2026 (released publicly on July 16, 2026), the Board held that it was bound by the Freedom of Information Act (“FOIA”) and its own rules to publish the decision, and that the Corps had not demonstrated a basis for overcoming that requirement.  This decision is noteworthy not only because the Board found no legal basis to suppress the opinion, but also because, as the Board observed, such a request had never before been directly presented to the Board.

The Board’s decision stems from three appeals brought by KiewitPhelps involving the construction of the new command facility for the U.S. Strategic Command at Offutt Air Force Base, Nebraska.  On May 4, 2026, the Board issued a 148-page decision addressing KiewitPhelps’ delay and disruption claim, one of three related appeals arising from the project.  Because the appeal was subject to a protective order, the decision was not immediately made public, and the Board, pursuant to its standard procedures, gave the parties an opportunity to propose redactions consistent with FOIA exemptions.  Rather than propose redactions, however, the parties returned to the Board with a “Joint Motion for Consent Judgment to Effectuate Global Settlement,” contingent on the Board not publishing its May 4 decision. 

The Board convened a status conference and, as a matter of courtesy, informed the parties that the decision would need to be public and that pursuing the motion might only draw additional attention to the underlying opinion.  The Board also offered the parties the opportunity to withdraw the motion before issuing a ruling.  The Corps declined and instead asked to provide supplemental briefing on the issue.[1]  KiewitPhelps, by contrast, did not submit additional briefing.  As the Board noted, KiewitPhelps’ primary interest appeared to be securing payment under the parties’ settlement and avoiding the cost of further litigation, rather than advancing an independent argument for non-publication.

The Corps advanced several arguments in support of withholding the decision, all of which the Board rejected.  First, the Corps asserted that because the Contract Disputes Act (“CDA”) allows the Board to “issue a decision in writing or take other appropriate action on each appeal submitted,” 41 U.S.C. § 7105(g) (emphasis added), the phrase “other appropriate action” could encompass declining to publish a decision.  Second, the Corps asserted that the Board’s decision was not yet final because it addressed only entitlement and not quantum and therefore could not yet be appealed to the Federal Circuit.  Finally, the Corps argued that, if viewed as a request for vacatur, the request should be granted on the equities.  The Board rejected each argument. 

The CDA Does Not Authorize the Board to “Unpublish” Decisions

First, the Board rejected the Corps’ reliance on the CDA’s authorization to “take other appropriate action” on an appeal.  The Corps argued that this language gave the Board discretion to forgo publication of the May 4 decision as part of the parties’ settlement.  The Board disagreed, finding no support for the notion that the CDA’s catch-all language permits the Board to suppress an already issued and authenticated decision.  Although the Board acknowledged its authority to take “other appropriate action” in resolving appeals, it concluded that any such authority must be exercised consistently with the Board’s rules and other applicable law.  Here, ASBCA Rule 19 and FOIA pointed in the opposite direction, requiring public disclosure absent a recognized basis for confidentiality.  In the Board’s view, the Corps was effectively asking it to disregard those obligations without identifying any legal justification for doing so.  

A Decision Can Be Final for Publication, Even If Not Yet Appealable

Second, the Board rejected the Corps’ argument that the May 4 decision was not yet final.  The Corps argued that because the decision addressed entitlement but not quantum, it was not appealable to the Federal Circuit and therefore was not the type of final decision that FOIA requires agencies to publish.  The Board disagreed, explaining that the Corps had conflated finality for purposes of appellate jurisdiction with finality for purposes of the Board’s own rules and procedures.  Although an entitlement-only decision may not yet be appealable, the Board explained that such decisions are nevertheless final Board decisions: they close the appeal before the Board, are subject to motions for reconsideration, and are treated as precedential in the same manner as decisions that address both entitlement and quantum. 

Having concluded that the decision was final for the Board’s purposes, the Board found that both ASBCA Rule 19 and FOIA required publication absent a recognized basis for confidentiality.  The Board explained that its rules are consistent with FOIA, which requires that “[e]ach agency, in accordance with published rules, shall make available for public inspection in an electronic format – (A) final opinions, including concurring and dissenting opinions . . . .”  5 U.S.C. § 552(a)(2).  Because the Corps identified no applicable FOIA exemption to justify suppressing the decision, there was no basis to override the statutory requirement.  The Board likewise rejected the Corps’ invitation to avoid FOIA’s publication requirement by designating the opinion as non-precedential. 

Settlement Is Not a Basis to Erase a Decision

Finally, the Board rejected the Corps’ suggestion that the requested relief could be justified under principles governing vacatur.  Citing the Supreme Court’s decision in U.S. Bancorp Mortgage Co. v. Bonner Mall Partnership, 513 U.S. 18, 26 (1994), the Board emphasized that vacatur is an “extraordinary remedy” reserved for exceptional circumstances.  The Board found that the Corps had not identified any such circumstances, noting that its principal justification was that confidentiality had become a condition of the parties’ global settlement agreement.  That justification, the Board explained, was not enough.  The Board further observed that the public interest weighed against withholding the decision, particularly where one of the parties was the Federal government and the dispute involved the expenditure of public funds.  In short, the Board declined to allow settlement concerns, standing alone, to overcome the strong public interest in maintaining and publishing Board-issued decisions.

A Problem of the Corps’ Own Making

In supplemental briefing, the Corps raised an additional argument regarding appellant review.  The Corps argued that because the Board’s decision addressed only entitlement and left quantum unresolved, the Government would not yet be in a position to evaluate any potential appeal.  Indeed, as the Federal Circuit recently reiterated in Secretary of Defense v. Pratt & Whitney, 160 F.4th 1224, 1231 (Fed. Cir. 2025), Board decisions ordinarily are not appealable while quantum remains pending.  However, the Board found the Corps’ complaint unpersuasive because the Corps itself had requested bifurcation of entitlement and quantum, over KiewitPhelps’ objection.  In the Board’s view, the Corps could not complain about “the appellate consequences of getting what it wanted.”  See Decision on Joint Motion for Consent Judgment at 5.  The Board further noted that if the Corps truly wished to expedite appellate review, it could simply stipulate to quantum and obtain a final judgment.  Accordingly, the Board viewed the Corps’ inability to immediately pursue appellate review not as a basis to suppress the decision, but as the foreseeable consequence of a litigation strategy of its own making.

The Public’s Interest in Publication of Board Decisions

At its core, the Board’s decision is a reaffirmation of the principle that judicial decisions are presumptively public.  Throughout the opinion, the Board repeatedly emphasized that publication is not a matter of discretion or party preference, but a requirement grounded in its rules and FOIA.  Absent a recognized basis for confidentiality, Board-issued decisions belong in the public domain.

The Board viewed that principle as particularly important in the government contracts context, where disputes concern the expenditure of taxpayer funds and the administration of public contracts.  In explaining the public interest in publication of the KiewitPhelps decision, the Board observed that contractors should be able to see that their “legitimate complaints will be treated seriously and remedied, when appropriate, in accordance with the law.”  See Decision on Joint Motion for Consent Judgment at 8.  But that interest extends beyond any particular litigant or outcome.  Whether a decision favors the government or the contractor, whether the request for confidentiality comes from the agency or the private party, and whether publication is viewed as beneficial or embarrassing to either side, the same principle applies: disputes involving public funds and public contracts are generally resolved in public, and the public has a legitimate interest in understanding how those disputes are decided.

The decision also sends a clear signal that parties should not assume a post-decision settlement can remove a Board-issued opinion from public view.  As the Board observed, it had never before been directly asked to grant the relief sought by the Corps and had no intention of starting on the facts presented here.  In light of this decision, litigants before the Board that perceive a risk of harmful precedent should consider pursuing settlement or Alternative Dispute Resolution before the Board issues a final decision.

Whether the parties ultimately proceed with their proposed settlement despite the Board’s refusal to withhold publication remains to be seen.  Regardless, the decision stands as a notable affirmation of the strong presumption that ASBCA decisions, absent a valid basis for confidentiality, should remain available for public scrutiny.


[1] While it is not clear precisely why the Corps wanted the decision to be withheld from public view, the Board’s decision hints that the Corps may have been concerned about harmful precedent. See Decision on Joint Motion for Consent Judgment at 6 (referring to “the unspoken suggestion that what the Corps is truly concerned about is the precedential authority of the decision”).

Photo of Elizabeth Witwer Elizabeth Witwer

Elizabeth Witwer represents government contractors litigating contract claims and performance disputes against the U.S. government and other contractors, such as claims under the Contract Disputes Act (CDA), defective pricing claims, cost-allowability disputes, prime-sub disputes, and matters involving termination for convenience and breach of…

Elizabeth Witwer represents government contractors litigating contract claims and performance disputes against the U.S. government and other contractors, such as claims under the Contract Disputes Act (CDA), defective pricing claims, cost-allowability disputes, prime-sub disputes, and matters involving termination for convenience and breach of contract. She litigates cases in a variety of venues, including the Boards of Contract Appeals and the U.S. Court of Federal Claims (COFC).

Elizabeth joined the firm after serving as an Administrative Judge on the Armed Services Board of Contract Appeals (ASBCA), where she was responsible for adjudicating disputes arising under the CDA between contractors and federal agencies, including the Department of Defense, NASA, and the CIA.

Prior to serving at the ASBCA, Elizabeth held overlapping positions at the U.S. Government Accountability Office (GAO) as a Senior Attorney in the Procurement Law Division and as a member of GAO’s Contract Appeals Board. In these roles, she dual-hatted as adjudicator of bid protests challenging federal procurements and presided over contract disputes between contractors and legislative branch agencies.

Earlier in her career, Elizabeth served as a Trial Attorney in the Civil Division of the Department of Justice, where she defended the United States and federal agencies in contract, employment, and constitutional disputes before the U.S. Court of Appeals for the Federal Circuit and the COFC. She also served on active duty in the U.S. Army as counsel to the Army’s Legal Services Agency and the 4th Infantry Division on procurement matters and contract litigation, including while deployed to Iraq.

In addition to her legal practice, Elizabeth is a Colonel in the U.S. Army Reserve. 

Photo of Daniel Russell Jr. Daniel Russell Jr.

Dan Russell represents government contractors in complex, high-stakes litigation. Over the past two decades, Dan has served as lead counsel for some of the largest U.S. defense contractors in a broad range of contract disputes and tort claims, including cases valued well in…

Dan Russell represents government contractors in complex, high-stakes litigation. Over the past two decades, Dan has served as lead counsel for some of the largest U.S. defense contractors in a broad range of contract disputes and tort claims, including cases valued well in excess of $100 million.

Dan has experience litigating contract claims and disputes before federal judges and juries, the Boards of Contract Appeals, and the U.S. Court of Federal Claims, including matters arising out of terminations, cost-allowability disputes, defective pricing claims, prime-sub disputes, and claims under the Contract Disputes Act (CDA). Dan has also represented contractors in a myriad of tort suits arising out of work performed for the federal government. Dan has unparalleled experience defending “contractor on the battlefield” tort suits involving contracts performed during wartime or other high-risk, contingency environments. Dan has obtained complete dismissals of tort suits based on an array of federal-law-based defenses, including the government contractor defense, the political question doctrine, federal preemption, and derivative sovereign immunity.

Dan has litigated a variety of other matters involving government contracts and uniquely-federal issues, including: cases brought under the civil False Claims Act (FCA); insurance coverage matters for federal contractors; claims against federal agencies brought under the Administrative Procedure Act and the Federal Tort Claims Act; and regulatory enforcement actions.

At the appellate level, Dan has argued cases before the U.S. Courts of Appeals for the Fourth Circuit, the Fifth Circuit, and the Ninth Circuit. He has also represented clients in matters before numerous other appellate courts and the U.S. Supreme Court.

In addition to his litigation practice, Dan regularly provides risk-mitigation counseling for contractors, with a particular focus on strategies to reduce potential exposure to tort claims and other liabilities in connection with the performance of high-risk government contracts.

Photo of Jennifer Bentley Jennifer Bentley

Jennifer Bentley represents government contractors in a range of matters, with an emphasis on litigation, investigations, claims and disputes, and regulatory counseling. She also has deep expertise in government contracts domestic sourcing and supply chain issues, including the Buy American Act, Trade Agreements…

Jennifer Bentley represents government contractors in a range of matters, with an emphasis on litigation, investigations, claims and disputes, and regulatory counseling. She also has deep expertise in government contracts domestic sourcing and supply chain issues, including the Buy American Act, Trade Agreements Act, Build America, Buy America, and the BIOSECURE Act.

She has represented government contractors in False Claims Act investigations, prime-subcontractor disputes in federal court, disputes before the Armed Services Board of Contract Appeals, cost accounting disputes, and bid protests at the Government Accountability Office and U.S. Court of Federal Claims. She maintains an active pro bono practice.